Project Timeline

 

 

 

Major Drainageway

Plan and FHAD

Deliverable/Milestone

Completion Date

Status

Notice to Proceed

 

4/30/2010

Phase A - Development of Alternatives

 

 

Baseline Hydrology Report (Draft)

7/23/2010

Completed

Baseline Hydrology Report (Final)

10/6/2010

 Completed 

Phase A Alternatives Report (Draft)

12/15/2010

Completed

Phase A Alternatives Report (Final)

8/30/2011

Completed

Select Alternative

10/17/2011

 Completed 

 

 

 

Phase B - Conceptual Design

 

 

Phase B - Conceptual Design Report (Draft)

12/16/2011

Completed

Phase B - Conceptual Design Report (Final)

1/23/2012

In Progress 

 

 

 

FHAD

 

 

FHAD (Draft)

4/29/2011

Completed

FHAD (Final)

12/15/2011

Completed