Project Timeline
|

|
Major Drainageway Plan and FHAD |



|
Deliverable/Milestone |
Completion Date |
Status |
|
Notice to Proceed |
|
4/30/2010 |
|
Phase A - Development of Alternatives |
|
|
|
Baseline Hydrology Report (Draft) |
7/23/2010 |
Completed |
|
Baseline Hydrology Report (Final) |
10/6/2010 |
Completed |
|
Phase A Alternatives Report (Draft) |
12/15/2010 |
Completed |
|
Phase A Alternatives Report (Final) |
8/30/2011 |
Completed |
|
Select Alternative |
10/17/2011 |
Completed |
|
|
|
|
|
Phase B - Conceptual Design |
|
|
|
Phase B - Conceptual Design Report (Draft) |
12/16/2011 |
Completed |
|
Phase B - Conceptual Design Report (Final) |
1/23/2012 |
In Progress |
|
|
|
|
|
FHAD |
|
|
|
FHAD (Draft) |
4/29/2011 |
Completed |
|
FHAD (Final) |
12/15/2011 |
Completed |